The technical staffs of AN-GEO have led hundreds of environmental projects in the past. Included in
these projects were studies for operation review, management planning, environmental audits, impact and
risk evaluations, landfill studies, preacquisition site assessments, contamination studies, hydrogeological
evaluations, underground storage tank investigations, site remediations, design of monitoring systems,
expert consulting for legal firms, and implementation of mitigative measures. In addition, the services
provided included project management, construction observations and monitoring of rehabilitation for
both existing sites and new facilities.
This experience is highlighted by the selected projects described below:
Technical Consulting for Litigation
Acted as a specialist consultant to solicitors in litigation matters with respect to
environmental liability issues including contaminated sites and hazardous waste problems
such as biological, metals, radioactive nuclei, PCB, PCP, PERC, TCA, creosote, dioxins,
furans, petroleum and agricultural based contaminants assessment, delineation and
remediation. Input included reviewing technical reports and project history as well as
conducting independent investigations for advice regarding possible claims, compliance,
appeal of control orders and regulatory decisions. Problem solving strategy was
recommended. Involvement also included participation in negotiation, discovery, board and
court testimony.
Property Environmental Liability Assessment
Served as advisor to governmental agents, financial institutions, developers, builders, owners
and property managers on issues of environmental liabilities associated with various assets
including public, residential, medical, retail, industrial, fuel storage and distribution facilities.
Tasks included assessing implications for site contamination such as mold problems with
respect to financing, insurance requirements, civil and regulatory obligations for prospective
Environmental Management Program
Participated as a specialist consultant in the production and implementation of environmental
management programs (EMP) for a major municipality, military base, eight steel plants and
various business locations of a waste management and an international construction company
in Canada. Objective was to ensure legal compliance and promote operations stressing safe
work practices and preserving facility assets. Tours of facilities were conducted to identify
operational aspects having environmental compliance and liability implications. Findings
were consolidated to develop standard operating procedures (SOP), instruction programs,
training materials and emergency response manuals (ERM) for functional adaptation.
Underground Fuel Storage Tank Investigations
Assessed the nature and extent of hydrocarbon contamination associated with underground
storage installations at numerous sites located in the Edmonton metropolitan area as well as
other locations in western Canada. In many cases, remediation plans were devised, managed
and documented in completion reports for the clients and regulatory agencies.
Contaminated Site Health Impact Management Action Plan
Developed and designed a master action plan to inventory, rank and manage possibly
problematic as well as contaminated sites with respect to health impacts for a major city in
Alberta. Detailed methodology for every analogical component was provided.
Environmental Impact Assessment
Investigated the environmental impact of a source facility for a major city in Alberta.
Assignment included 24 hour ambient air monitoring of inhalable and respirable harmful
particulates at perimeter locations off emission areas on six day cycles over three months.
Environmental effects, exposure and liability risks for a nearby golf course, specific
residences, an anticipated school and sport complex development in the vicinity were
addressed. A ten-year projection was included for planning subsequent actions. Various
options with estimated costs were presented for remediation works, monitoring and
confirmation studies as well as contingent measures. Recommendations were made with due
considerations of civil and regulatory implications.
Industrial Separation and Land Use Restriction Study
Examined documents in support of proposed separation distance and land use restriction bylaws
to be implemented at a heavy industrial subdivision for a major city in Alberta.
Recommendations regarding risk assessment and management were presented. Technical
support included attendance in council and public hearings.
Oil and Gas Development Impact Evaluation
Advised board of trustees on position and need for safe operation of a school in a vicinity
with approaching sour well development. Tasks included review of proponent submission
materials for licence applications, assistance in negotiation for settlement of selected
facilities, provision of technical support for trustee conferral sessions and regulatory hearing
proceedings. Assignment covered checking of proponent contaminant dispersion modeling,
emergency response plans, incident and health risk evaluation results.
Indoor Air Quality Problem Assessment
Assisted a municipal government in Alberta to resolve indoor air quality complaints by civic
employees in a leased office building. Reviewed other consultant reports on causes,
conducted independent investigations and provided suggestions for related matters in dealing
with landlord, worker compensation claim, public health authority as well as identification of
alternate premise for relocation. Involvement was extended to working with public work
department staff in implementation of a decontamination program for in-house properties by
city engaged restoration service providers.
Military Installation Remediation Study
Characterized the stratigraphy and groundwater behaviour in the designated area for
remediation of migrating “lighter” and “denser than aqueous phase liquid” (LNAPL and
DNAPL) contaminants. Evaluated feasible remedial options including management by
natural attenuation. Findings were used in identification of design parameters for system
design.
Circuit Board Manufactory Residual Contamination Assessment
Evaluated level of airborne chemical contaminants accumulated on walls, ceiling and within
venting ducts. Swab sampling and confirmatory testing data were used to project impact risk
of release for building occupants. Recommendations were provided to remedy the
contamination problems and restore the existing facilities. Issues of waste management and
safety protection were also addressed.
Burn Site Assessment and Hazardous Debris Removal
Characterized material nature of fire remnants at a waste processing plant. Established waste
management options. Evaluated option feasibility. Formulated debris removal plan. Acquired
regulatory approval. Conducted contract procurement. Supervised field works for the site
clearing and produced decommissioning documentation for redevelopment proceedings.
Tailing Pond Impact Monitoring
Assessment and Remediation
Maintained annual monitoring of contaminant influx on land close to tailing storage facility
for a chemical production plant. Well sampling and testing were executed for evaluation of
organic, inorganic and isotope parameters. Hydrogeological data were collected to establish
seepage patterns for source identification. Field indicator tests were conducted for target
aquifers in equilibrium assessment. Involvement included preparation of evidence for
presentation in public hearing and assistance in action for appeal of regulatory position.
Public Transport Facility Installation Decommissioning, Subsurface Contamination
Assessment and Remediation
Served as advisor to public works authority in decommissioning a pavement heating system
with hazardous chemical holding at the service and fueling area of a municipal garage. Tasks
included formulation of action plan, design of waste management and treatment process. The
contractor undertakings were monitored and advice was provided to resolve technical
problems encountered. The extent and impact of release from the pavement heating and
fueling operations were delineated. A risk assessment was conducted and a management
strategy was recommended. Subsequent involvement included acquisition of regulatory
approval, design of a trench recovery system for retrieval of escaped product, provision of
improvement recommendations for existing dispensary installations, development of
construction plan, preparation of work specifications, assisting contract procurement and
supervision of implementation activities.
Laundry Plant Site Contamination Review
Act as specialist consultant to deal with dry cleaning solvent contamination for a commercial
processing plant. Assignment included review of previous investigation undertakings as cross
contamination causes for liability pursuit consideration. Additional sampling and testing
were conducted to verify site conditions. The associated facility installations, equipment
maintenance and operation practice were examined for evaluation of possible release nature
and duration. Recommendations were provided for status delineation, equipment repair and
activity improvement.
Privatization Study for Arctic Bulk Fuel Storage and Distribution Facilities
Participated in the development of valuation and privatization methodology for bulk fuel
assets in 44 northern communities. Formulated an algorithm for planning the condition
evaluation works. The organization of this algorithm included contemplation of unique
northern environment, setting characteristics and nature of use for the installations. A process
was established to identify facilities with contamination and compliance problems that would
require improvement through remediation and upgrading.
Arctic Environmental Assessment
Conducted land use historical review, field screening, sampling and testing to assess nature of
surface abandoned materials and extent of ground contamination for a site in Nunavut.
Ecological impact risk was evaluated. Response action plan was formulated with priority
ranking recommendations.
Licensing for Hazardous Recyclable and Industrial Waste Processing Plant
Attended to the development and preparation of baseline environmental assessment,
operation impact evaluation, incoming waste quality assurance, incinerator feed verification,
closure and post closure monitoring program plans required for permit application.
Assignment was extended to undertaking assessment and monitoring works on a continuous
basis as per license specifications.
Hazardous Waste Transfer Station and Landfill Study
Reviewed the original site investigation, impact studies, facility operation and development
plan for a hazardous waste transfer station and landfill site in Alberta. Compliance with
regulatory requirements with respect to legislation and standing permits was evaluated.
Public health and environmental risks caused by the subject installations to the surroundings
were assessed.
Airport Terminal Building and Airfield Construction Site Subsurface Contamination Evaluation
Investigated and delineated subsurface contamination at the site of a proposed terminal for an
airport in Northwest Territories. Task included recommendations and design for remedial
measures to reinstate the site to acceptable conditions for a public facility.
Pipeline Terminal Spill Evaluation
Investigated the nature of release, emergency response actions and residual contamination at
a distribution centre in Western Canada. Ecological impact was evaluated by material
testing, plume modeling, fate projection and risk analysis for target receptors.
Chemical Storage Facility Permit Application
Conducted a detailed operation review and setting study for an Albertan chemical storage
facility in pursuit of government operation permit. The setting study involved identification
of potential environmental impacts in development of biannual monitoring scheme for
compliance monitoring. The project scope also included extensive sampling and testing for
filing as base reference after acquisition of regulatory approval.
Chroming Plant Contamination State Review
Acted as specialist consultant to assist a Canadian expanding industry in pursuit of business
interest for a chroming plant with known contamination problems. Initial assessment
involved conciliation and analysis of available site data to estimate current conditions for use
in development of negotiation strategy. Supplementary investigation was conducted.
Findings were correlated with previously reported results for confirmation of existing state in
drafting of transaction documents.
Highway Expansion Contamination Remediation
Served as advisor to a Western Canadian public works authority in resolving subsurface
contamination problems at a highway expansion site. Involvement included development of
remedial program completed with treatment facility design, attendance of community
meetings for public consultation, liaison with multiple levels of regulatory agencies for
activity approval, preparation of job specifications for tender and provision of technical
assistance to client project manager over implementation of the mitigation and restoration
works.
Agricultural Chemical Transfer Station Site Feasibility Study
Provided technical assistance for the planning and design of an agricultural chemical storage
complex in British Columbia. Recommendations included special design features against
accidental release and spill of chemicals.
Landfill Siting Evaluation
Evaluated the site selection for a proposed county landfill in northern Alberta. Compatibility
of the proposed landfill with respect to local geological and hydrogeological settings was
assessed.
Liner Design and Construction Planning
Provided expert resource in the planning of liner design and construction for an industrial
hazardous waste landfill in China. Input included methodology for system analyses, feature
optimization, design rationale, selection of materials, identification of borrow areas, quality
control testing, site preparation, construction monitoring and operating verification.
Landfill Expansion Studies
Examined the development plans for operating landfills in Alberta and China. The planning,
analysis and design for acquisition of additional facilities for waste disposal, recycling and
utilization were investigated. The China project included provisions for landfill gas
production. Environmental and public health risks were considered.